Shasta-Trinity National Forest OHV Ground Operations
Program
Rural Roads Improvements
Primary RCD
Trinity County Resource Conservation District
Lead Implementer
Trinity County Resource Conservation District
Funders
California Department of Parks and Recreation
Project Primary Contact
Patrick Flynn (pflynn@tcrcd.net)
Project Stage
Completed
Duration
2018
Water Quality Improvement
Rural Roads Improvements
Ground operations within the Shasta-Trinity National Forest, South Fork Trinity River Watershed. Project activities include, but are not limited to, traffic control, signage repair and installation, brush removal, removal of route hazards, erosion and/or sediment control.
Key Accomplishments
- Roads Treated for Pollutant Reduction: 57.00 miles
Project Themes
- Forests and Fire
- Groundwater
- Healthy Watersheds
FS Road 28N10G at mile marker 0.35 - After. 100% plugged culvert at stream crossing was excavated, extensive brushing to open route was also completed.
Credit: C. Tarwater - Trinity County RCD
Location
Expenditures
Expenditures by Funding Source to Date: $39,447.00
OHV Recreation Division Progr... (CDPR): $39,447
Photos
FS Road 28N10G at mile marker 0.35 - Before. Road was overgrown and washed out.) (Timing: Before)
Credit: C. Tarwater - Trinity County RCD
FS Road 28N45 - Prior to brushing and logout work (Timing: Before)
Credit: Trinity County RCD
FS Road 28N45 - After brushing overgrown route and logout (Timing: After)
Credit: Trinity County RCD
FS Road 28N45 at mile marker 1.82 - 100% plugged culvert at stream crossing was opened to protect route, extensive brushing was also completed on this route. (Timing: After)
Credit: Trinity County RCD
Project last updated 1/5/2022